Mallards Dairy Streambank Restoration Project Closeout Report

Thanks to the commitment of Mallards Dairy and their enthusiasm for this project it was successfully completed in the spring of 2018. It represents a demonstration of the efficacy of applying bioengineering techniques in streambank restoration. The success of this first streambank restoration project laid the groundwork for future projects. We have completed another similar project in 2019 to similarly stabilize 1,800 feet of river bank at Edelweiss Farms and have two more on the books for 2020. This work totals to 7,700 linear feet of streambank restoration.